How many S-60 watchpersons does a site need, and how is S-60 different from F-01?

A construction site with a building footprint between 5,000 and 40,000 square feet needs at least one S-60 watchperson, plus one more for each additional 40,000 square feet or part of it. The S-60 is its own certificate with its own test, so it does not let you do the work of an F-01, S-56, S-92 or any other certificate.

New York · Fire · Entry level2 min read

Prepared independently by RankHigh from Fire Department of the City of New York (FDNY), Bureau of Fire Prevention -- Public Certification Unit’s published material. Not affiliated with or endorsed by Fire Department of the City of New York (FDNY), Bureau of Fire Prevention -- Public Certification Unit.

On this page
  1. The staffing rule
  2. When the watchperson is on duty
  3. The other construction-site certificates
  4. S-60 versus F-01
  5. Sources

At a glance

Footprint trigger
5,000 to 40,000 square feet: at least one S-60 watchperson
Larger sites
One more per additional 40,000 square feet or fraction
On-duty period
When operations are not in progress, from foundation pour until the certificate of occupancy or TCO
Required since
03/01/2016

The staffing rule

The booklet bases the number of watchpersons on the building's footprint. Sites between 5,000 and 40,000 square feet need at least one. For each further 40,000 square feet, or any part of that amount, the site needs another watchperson.

The booklet also describes two exceptions that allow fewer watchpersons. Expect test questions that give you a footprint or a situation and ask how many watchpersons are needed.

New York

Certificate of Fitness S-60 -- Watchperson at Construction Sites (Citywide)

$79Your one-time purchase includes 90 days of access from the time payment clears. No subscription. No automatic renewal

  • Prepared scope and limits shown clearly
  • Targeted practice by weak area
  • Worked answer explanations
  • Missed-question and due-review queues
  • 90 days of access

Full details for this examRefund policy

When the watchperson is on duty

The watchperson covers the site when construction operations are not in progress. This requirement starts when the foundation is poured. It continues until the building receives a certificate of occupancy or a temporary certificate of occupancy.

The other construction-site certificates

The booklet's introduction has a table of ten Certificates of Fitness used on construction sites, each with its own duties. The S-60 covers only watchperson work. Holding it does not let you take on any of the other roles.

  • G-60, E-21, F-01, F-60, P-54
  • S-56, S-60, S-92, S-93, S-94
  • E-21: the booklet ties powder-actuated tool work to E-21 supervision
  • S-92: the booklet ties portable fueled heaters to S-92 supervision

S-60 versus F-01

The F-01 is FDNY's fire guard certificate, which includes construction-site fire guards. It shares some subjects with the S-60, such as extinguishers and lithium-ion batteries, but it has a different booklet and a different test.

Passing one of these tests does not give you the other certificate. RankHigh's S-60 practice is built only from the S-60 booklet.

Sources